Transforming
Property

140 William Heritage

Successful heritage preservation

With a fitout required across three separate heritage listed buildings, Building Management and Works required an experienced contractor who could ensure heritage preservation. SHAPE  utilised our demonstrated prior experience to maintain the heritage elements and ensure that no new works impacted the buildings.


The seven floors that required a fitout needed to be delivered on time to allow the IT staff to setup relevant data linkages and commissioning. SHAPE  achieved this through a highly collaborative approach, including having pre start meetings for key work scopes, weekly PCG meetings, regular design team inspections and constant communication with the base builders, client and the design team.

Client: Building Management and Works

Floor Area: 2,599 m²

Delivery Model: Lump sum

Location: Perth

State: WA

Project type: Fitout, Heritage, Government

Completion date: March 2012

Duration: 4.5 months

Architect: IA Group

Sector: Office Government

Download Project Profile(0.51 MB)